The project involves the construction of 2 trains of 4×10⁶ Nm³/d acid and water removal units, with supporting auxiliary engineering systems including thermal engineering, fire protection, water supply and drainage, and power distribution.
Key project components include:
17 building monomers
Approximately 1,600 meters of pipe racks
1,260 square meters of steel platforms
Acid Removal Skid Unit Specifications:
Total Length: ~44.8 m (including side diagonal ladders)
Width: ~15 m
Height: ~10.4 m
Feed Gas Operating Pressure:4.9 MPa
Application